RUBY CANYON


NORTH 11
10 OKTOBER 2024
Status :Pek.Galian Tanah Pondasi setempat
Progress : 2,60%

NORTH 11
17 OKTOBER 2024
Status :Pek.Pondasi menerus batu bata
Progress : 8,13%

NORTH 11
24 OKTOBER 2024
Status :Pek.Pembesian kolom
Progress : 13,00%

NORTH 11
31 OKTOBER 2024
Status :Pek.pasangan bata septitenk & resapan
Progress : 18,20%

NORTH 11
07 NOVEMBER 2024
Status :Pek.kolom beton & praktis
Progress : 20,81%

NORTH 11
14 NOVEMBER 2024
Status :Pek.pembesian kolom beton & Balok
Progress : 25,36%

NORTH 11
21 NOVEMBER 2024
Status :Pek.pengecoran plat lt 2
Progress : 29,26%

NORTH 11
28 NOVEMBER 2024
Status :Pek.pembesian kolom beton 12/40 (K1)
Progress : 31,01%

NORTH 11
05 Desember 2024
Status :Pek.pas dinding batubata lt.2
Progress : 34.17%

NORTH 11
12 Desember 2024
Status :Pek.pembesian plat lantai 3 + bekisting
Progress : 37,52%

NORTH 11
19 Desember 2024
Status :Pek.pembesian balok beton 25/60 (B4)
Progress : 39,99%

NORTH 11
26 Desember 2024
Status :Pek.pembesian kolom beton 12/40 (K1)
Progress : 41,85%

NORTH 11
02 Januari 2025
Status :Pek.pasangan dinding batu bata lt.3
Progress : 44,97%

NORTH 11
09 Januari 2025
Status :Pek.cor ring balok 12/15 besi
Progress : 50,08%

NORTH 11
16 Februari 2025
Status :Pek.Plesteran dinding lt.1, lt.2, lt.3
Progress : 53,81%

NORTH 11
23 Januari 2025
Status :Pek.Plesteran dinding lt.1, lt.2, lt.3
Progress : 57,49%

NORTH 11
30 Januari 2025
Status :Pek.Plesteran dinding lt.1, lt.2, lt.3
Progress : 58,53%

NORTH 11
06 Februari 2025
Status :Pek.Acian dinding lt.1
Progress : 60,29%

NORTH 11
13 Februari 2025
Status :Pek.meja dapur
Progress : 63,74%

NORTH 11
20 Februari 2025
Status :Pek.Acian dinding luar dalam lt.1,2,3
Progress : 65,62%

NORTH 11
27 Februari 2025
Status :Pek.pas granit dinding kamar mandi lt.2
Progress : 67,75%

NORTH 11
06 Maret 2025
Status :Pek.plesteran dinding lt.1,2,3
Progress : 69,83%

NORTH 11
13 Maret 2025
Status :Pek.pas keramik lantai lt.3
Progress : 75,29%

NORTH 11
20 Maret – 10 April 2025
Status :Pek.pas granit lantai lt.1,2, & 3
Progress : 77,91%

NORTH 11
17 April 2025
Status :Pek. Cat dinding lt.1, lt.2, lt.3.
Progress : 79,86%

NORTH 11
24 April 2025
Status :Pek.pas kusen Almunium lt.1, lt.2
Progress : 83,98%

NORTH 11
02 Mei 2025
Status :Pek. Ris bata taman depan.
Progress : 85,00%

NORTH 11
08 Mei 2025
Status :Pek.pas granit lantai kamar mandi lt.2.
Progress : 86.27%

NORTH 11
15 Mei 2025
Status :Pek. Pas floordrain kamar mandi lt.1.
Progress : 87.26%

NORTH 11
22 Mei 2025
Status :Pek. Pas kran air amar mandi lt.1.
Progress : 89,74%

NORTH 11
30 Mei 2025
Status :Pek. Pas plafond gypsum lt.1, lt.2, & lt.3.
Progress : 93,42%

NORTH 11
05, 12 dan 19 Juni 2025
Status :Pek.pas aksesoris kamar mandi lt.1.
Progress : 93,42%

NORTH 11
28 Juni 2025
Status :Pek pas braket kaca skylight.
Progress : 94,12%

NORTH 11
03 Juli 2025
Status :Pek.pembersihan akhir.
Progress : 95,49%

NORTH 11
10 Juli 2025
Status :Pek.pembersihan akhir.
Progress : 96,34%

NORTH 11
17 Juli 2025
Status :Pek.pembersihan akhir.
Progress : 97,70%

NORTH 11
24 dan 31 Juli 2025
Status :Pek.pembersihan akhir.
Progress : 98,85%

NORTH 11
07, 14, 21 dan 28 Agustus 2025
Status :Pek.pas ralling tangga.
Progress : 99,35%

NORTH 11
04 September 2025
Status :Pek.pembersihan akhir.
Progress : Mencapai 100%