COPPER CANYON


SOUTH 7
14 November 2024
Status :Pek.galian pondasi tapak
Progress : 1,15%

SOUTH 7
21 November 2024
Status :Pek.pembesian tapakan
Progress : 3,28%

SOUTH 7
28 NOVEMBER 2024
Status :Pek.pembesian kolom beton
Progress : 6,55%

SOUTH 7
05 Desember 2024
Status :Pek.galian tanah pondasi menerus bata
Progress : 9,41%

SOUTH 7
12 Desember 2024
Status :Pek.cor sloof beton
Progress : 13,12%

SOUTH 7
19 Desember 2024
Status :Pek.pasangan dinding batu bata
Progress : 15,61%

SOUTH 7
26 Desember 2024
Status :Pek.perataan tanah kembali
Progress : 19,59%

SOUTH 7
02 Januari 2025
Status :Pek.Bekisting plat lantai 2
Progress : 22,79%

SOUTH 7
09 Januari 2025
Status :Pek.pembesian plat lantai lt.2
Progress : 27.79%

SOUTH 7
16 Januari 2025
Status :Pek.Pasangan bata dinding lantai 2
Progress : 31.91%

SOUTH 7
23 Januari 2025
Status :Pek.cor kolom beton
Progress : 35,59%

SOUTH 7
30 Januari 2025
Status :Pek.pembesian balok beton
Progress : 40,29%

SOUTH 7
06 Februari 2025
Status :Pek.pembesian ring balok
Progress : 43,12%

SOUTH 7
13 Februari 2025
Status :Pek.pas dinding bata lt.3
Progress : 46,03%

SOUTH 7
20 Februari 2025
Status :Pek.pas granit dinding kamar mandi lt.2
Progress : 50,39%

SOUTH 7
27 Februari 2025
Status :Pek.bekisting tangga
Progress : 54,75%

SOUTH 7
06 Maret 2025
Status :Pek.acian dinding lt.1
Progress : 59,34%

SOUTH 7
13 Maret 2025
Status :Pek.pas granit dinding kamar mandi lt.2
Progress : 75,29%

20 Maret 2025
Status :Pek.plesteran dinding lt.2&3
Progress : 68,22%

27 Maret 2025
Status :Pek.acian dinding lt.3
Progress : 73,08%

10 April 2025
Status :Pek.Plesteran dinding dalam septitenk
Progress : 77,09%

SOUTH 7
17 April 2025
Status :Pek. Acian dinding Lt.1, Lt.2.
Progress : 80,17%

SOUTH 7
24 April 2025
Status :Pek.pengecatan dinding lt.1
Progress : 84,35%

SOUTH 7
02 Mei 2025
Status :Pek.pas granit lantai kamar mandi lt.2.
Progress : 88,35%

SOUTH 7
08 Mei 2025
Status :Pek.plesteran dinding lt.1, lt.3.
Progress : 91,79%

SOUTH 7
15 Mei 2025
Status :Pek.pas aksesoris kamar mandi lt.1, lt.2.
Progress : 94,71%

SOUTH 7
22 Mei 2025
Status :Pek.pas shower & jet washer kamar mandi lt.1.
Progress : 97,15%

SOUTH 7
30 Mei 2025
Status :Pek.finishing cat dalam & luar lt.1.
Progress : 99,38.%

SOUTH 7
05, 12, 19 dan 28 Juni 2025
Status :Pek pas kusen, jendela almunium.
Progress : 99,38.%

SOUTH 7
03, 10, 17, 24 dan 31 Juli 2025
Status :Pek.pas plafond.
Progress : 99,38.%

SOUTH 7
07 dan 14 Agustus 2025
Status :Pek.pas plafond.
Progress : 99,38.%

SOUTH 7
21 Agustus 2025
Status :Pek.pembersihan akhir.
Progress : Mencapai 100%