BLACK CANYON


SOUTH 1
10 MEI 2024
Status :Pek.Bowplank (Pengukuran)
Progress : 0,21%

SOUTH 1
17 MEI 2024
Status :Pek.galian tanah tapakan pondasi
Progress : 0,90%

SOUTH 1
24 MEI 2024
Status :Pek.Cor pondasi tapakan
Progress : 4,05%

SOUTH 1
30 MEI 2024
Status :Pek.pembesian sloof beton 20/30 besi dia.10 mm & 8 mm
Progress : 7,43%

SOUTH 1
13 JUNI 2024
Status :Pek.pasangan batu bata pondasi menerus
Progress : 13,72%

SOUTH 1
20 JUNI 2024
Status :Pek.pasangan dinding batubata lt.1
Progress : 17,01%

SOUTH 1
27 JUNI 2024
Status :Pek.bekisting kolom beton
Progress : 20,30%

SOUTH 1
04 JULI 2024
Status :Pek.Cor plat lantai tb.12 cm
Progress : 24,62%

SOUTH 1
11 JULI 2024
Status :Pek.Pasang kolom beton 14/40 & bekisting lt.2
Progress : 28,01%

SOUTH 1
18 JULI 2024
Status :Pek.Pasang dinding bata pagar belakang tedmond lt.2
Progress : 31,39%

SOUTH 1
25 JULI 2024
Status :Pek.Plesteran dinding lt.1
Progress : 34,91%

SOUTH 1
01 AGUSTUS 2024
Status :Pek.pembesian balok beton plat lantai 3
Progress : 39,61%

SOUTH 1
08 AGUSTUS 2024
Status :Pek.Kolom & bekisting kolom lt.3
Progress : 43,18%

SOUTH 1
15 AGUSTUS 2024
Status :Pek.Pasang batu bata dinding lt.3
Progress : 46,70%

SOUTH 1
22 AGUSTUS 2024
Status :Pek.Pas keramik dinding kamar mandi ART
Progress : 50,22%

SOUTH 1
29 AGUSTUS 2024
Status :Pek.setting tangga dan bekisting dari lt.2 ke lt.3
Progress : 53.74%

SOUTH 1
05 SEPTEMBER 2024
Status :Pek.Acian dinding lt.2
Progress : 57.27%

SOUTH 1
12 SEPTEMBER 2024
Status :Pek.pas granit dinding kamar mandi lt.2
Progress : 61.03%

SOUTH 1
19 SEPTEMBER 2024
Status :Pek.pas batubata septitank
Progress : 64.31%

SOUTH 1
26 SEPTEMBER 2024
Status :Pek.Plesteran dinding lt.1,lt.2 & lt.3
Progress : 67.83%

SOUTH 1
03 OKTOBER 2024
Status :Pek.Pas almunium foil + kawat ayam
Progress : 70.66%

SOUTH 1
10 OKTOBER 2024
Status :Pek.pas granit lantai lt.1,lt.2 & lt.3
Progress : 74.18%

SOUTH 1
17 OKTOBER 2024
Status :Pek.Pas atap Zigzag
Progress : 77.71%

SOUTH 1
24 OKTOBER 2024
Status :Pek.pas floor drain lt.1 & lt.2
Progress : 81.23%

SOUTH 1
31 OKTOBER 2024
Status :Pek.pas keramik lantai balkon lt.3
Progress : 84.53%

SOUTH 1
07 NOVEMBER 2024
Status :Pek.Cor deker
Progress : 87,92%

SOUTH 1
14 NOVEMBER 2024
Status :Pek.finishing plesteran + acian dinding
Progress : 90,50%

SOUTH 1
21 NOVEMBER 2024
Status :Pek.pas plafond lt.2 & lt.3
Progress : 92,50%

SOUTH 1
28 NOVEMBER 2024
Status :Pek.Cor caport
Progress : 93,72%

SOUTH 1
05 Desember 2024
Status :Pek.pas.aksesoris kamar mandi lt.1 & lt.2
Progress : 95,46%

SOUTH 1
12 Desember 2024
Status :Pek.pengecatan dinding dalam lt.1, lt.2 & lt.3
Progress : 95,94%

SOUTH 1
19 Desember 2024
Status :Pek.pas plafond lt.1, lt.2 & lt.3
Progress : 96,25%

SOUTH 1
26 Desember 2024
Status :Pek.pas kusen jendela+daun jendela+daun pintu almunium lt.1
Progress : 96,41%

SOUTH 1
02-16 Januari 2025
Status :Pek.pas plafond pvc. lt.3
Progress : 96,61%

SOUTH 1
23 Januari 2025
Status :Pek.pas conwood tampak muka
Progress : 96,98%

SOUTH 1
30 Januari 2025
Status :Pek.pas Jet washer kamar mandi lt.1
Progress : 97,22%

SOUTH 1
06 Februari 2025
Status :Pek.pengecatan conwood
Progress : 98,28%

SOUTH 1
13 Februari 2025
Status :Pek.pas bracket kaca skylight
Progress : 99,47%

SOUTH 1
20 Februari – 13 Maret 2025
Status :Pek.taman depan rumah
Progress : 99,47%

SOUTH 1
20 Maret – 10 April 2025
Status :Pek.Pasang interior
Progress : 99,47%

SOUTH 1
17-24 April 2025
Status :Pek.Pasang interior
Progress : Mencapai 100%

SOUTH 1
02-08 Mei 2025
Status :Pek.Pasang interior
Progress : Mencapai 100%

SOUTH 1
15, 22 dan 30 Mei 2025
Status :Sesuai.
Progress : Mencapai 100%

SOUTH 1
05, 12, 19 dan 28 Juni 2025
Status :Sesuai.
Progress : Mencapai 100%

SOUTH 1
03, 10, 17, 24 dan 31 Juli 2025
Status :Sesuai.
Progress : Mencapai 100%

SOUTH 1
07, 14, 21 dan 28 Agustus 2025
Status :Sesuai.
Progress : Mencapai 100%

SOUTH 1
04 September 2025
Status :Sesuai.
Progress : Mencapai 100%